Road: Belmont Avenue

Limits: Post Drive to Van Dam Drive

Work: Utility Work


Start: 07/19/21

Completion: 09/03/21


Traffic: Detour for Through Traffic

Authority: Utility

Contractor: Wyoming Excavators

Extension of water main along the west side of Belmont Avenue from Post Drive to Van Dam Drive.

  • Work conducted under flagging operation from July 19- July 23
  • Closure will begin on July 24 through August 6
  • Work after August 6 will be completed under flagging operation