Road: Lowell Township

Limits: Neighborhood Streets

Work: Resurfacing


Start: 06/06/22

Completion: 08/05/22


Authority: KCRC

Contractor: Michigan Paving and Materials

Funding: 50% KCRC/50% Lowell Township

KCRC in collaboration with Lowell Township is contracting with Michigan Paving & Materials to complete a full-width repaving of select local streets.

  • Baywicke Drive: Woodbushe Drive to Spicewood Drive
  • Berrywood Drive: Settlewood Drive to End
  • Deerwood Court: Deerwood Drive to End
  • Deerwood Drive: Sconcewood Drive to the End
  • Gingerwood Drive: Settlewood Drive to End
  • Huntwood Drive: Settlewood Drive to End
  • Junewood Court: Settlewood drive to End
  • Lockewood Drive: East and West of Woodbushe Drive
  • Sconcewood Drive: East and West of Woodgate Drive
  • Settlewood Drive: Parnell Avenue to Woodrun Drive
  • Spicewood Court: Spicewood Drive to End
  • Spicewood Drive: Woodbushe Drive to End
  • Stonewood Drive: Woodbushe Drive to End
  • Woodbushe Dr: Cumberland Ave. to 140' N/ of Baywicke Dr
  • Woodfern Drive: Settlewood Drive to End
  • Woodgate Drive: Woodbushe Drive to End
  • Woodpine Court: Settlewood drive to End
  • Woodrun Drive: North and South of Settlewood Drive