Project Details

< Back

Information

Road: Ada Drive

Limits: Forest Hills Avenue and Spaulding Avenue

Work: Mill and Fill


Start: 08/10/23

Completion: 08/18/23


Traffic: Detour for Through Traffic

Authority: KCRC

Contractor: Rieth-Riley Construction

Ada Drive from Forest Hills Avenue to Spaulding Avenue will be milled full depth then repave. Spaulding Avenue / Ada Drive intersection and Spaulding Avenue 375 ft. north to Connemara Court will be milled partial depth (2”) and repaved.