Road Limits Work Start Completion Authority Traffic
KCRC's Five-year Improvement Plan TBD TBD

DOWNLOAD: KCRC's Five-year Improvement Plan

Road Limits Work Start Completion Authority Traffic
Lincoln Lake Avenue Bradshaw Street to Lincoln Pines Crush & Shape 06/15/22 06/29/22 KCRC Detour for Through Traffic

This project includes a crush and shape of the existing asphalt surface and placement of two (2) courses of HMA.  Through traffic will be detoured.

Morse Lake Avenue 60th Street to 68th Street Crush & Shape 05/31/22 06/02/22 KCRC Detour for Through Traffic

This pavement replacement project consists of a crush & shape with new curb and gutter at 60th Street.

Algoma Township Neighborhood Streets Resurfacing TBD TBD KCRC Expect Delays

The Kent County Road Commission (KCRC) in collaboration with Algoma Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets. If you are receiving this letter, your street has been selected for resurfacing. The project is to be completed within contract limits, May 1 and August 31, 2022, weather permitting.

Current List of Roads

  • Reburn Drive: Hull Street south to End 
  • Tebeau Drive: Broman North to End

Information for Residents

Gaines Township Neighborhood Streets Resurfacing TBD TBD KCRC Expect Delays

The Kent County Road Commission (KCRC) in collaboration with Gaines Township is contracting with Superior Asphalt to complete a full-width repaving of select local streets.  The project is to be completed within contract limits, May 1 and August 31, 2022, weather permitting.

Current List of Roads to be Repaved

  • Bonnie Avenue: 68th St. to End
  • Brooklyn Avenue: Bonnie Avenue. to End
  • Crystal Valley Court: Old Lantern Drive to End
  • Crystalaire Court: Old Lantern Drive to End
  • Fairwood Court: Old Lantern Drive to End
  • Kings Crossings Court: Kings Crossing Drive to End
  • Kings Crossings Drive: Old Lantern Drive to Old Lantern Drive
  • Silver Springs Court: Old Lantern Drive to End
  • Plaza Center Drive: 68th Street to Market Place Drive

Information for Residents

Grand Rapids Township Neighborhood Streets Resurfacing TBD TBD KCRC Expect Delays

KCRC in collaboration with Grand Rapids Township is contracting with Michigan Paving & Materials to complete a full-width repaving of select local streets.

  • Amon Avenue: Elmer Drive to Valentine Street
  • Boyes Avenue: Elmer Drive to Maryland Avenue
  • Elmer Drive: Dean Lake Avenue to Maryland Avenue
  • Maryland Avenue: Elmer Drive to Valentine Street
  • Valentine Court: Dean Lake Avenue to End
  • Valentine Street: Dean Lake Avenue maryland avenue
  • Wilfrecd Avenue: Elmer Drive to Valentine Street
  • Arbor Chase Drive: Atwater Hills Drive to 3 Mile Road
  • Atwater Hills Drive: Mason Ridge Dr. to Arbor Chase Drive
  • Mason Ridge Drive: Dunnigan Avenue to Atwater Hills Drive 
  • Duchess Avenue: Reeds Lake to Reeds Lake Boulevard
  • Kate Avenue: Reeds Lake to Reeds Lake Boulevard
  • Lake Court: Reeds Lake to Duchess Avenue
  • McCoy Drive: Reeds Lake to Duchess Avenue
  • Reeds Lake: Reeds Lake Boulevard to Reeds Lake Boulevard

Morse Lake Avenue 68th Street to 60th Street Reconstruction TBD TBD KCRC
Byron Township Neighborhood Streets Resurfacing TBD TBD KCRC Expect Delays

KCRC in collaboration with Byron Township is contracting with Black Gord to complete a full-width repaving of select local streets.

  • 74th Street: Ardith Court to Clyde Park Avenue
  • Ardith Court: 73rd Street to End
  • Sierrafield Drive: 76th Street to 73rd Street
  • Athearn Drive: Westminister Drive to End
  • Chelmsford Drive: Althearn Drive to End
  • Westminister Court: West Minister Drive to End
  • Westminister Drive: Burlingame Avenue to Althearn Drive
  • Worthington Court: Worthington Street to End
  • Worthington Street: Burlingame Avenue to End
  • Glen Pond Drive: 68th Street to Pleasant Pond drive
  • Pleasant Glen Dr: Pleasant Valley Dr. to VanSingel Lake Dr.
  • Pleasant Hill Drive: Pleasant Pond Drive to Stub End
  • Pleasant Pond Drive: Pleasant Hill Drive to End
  • Pleasant Valley Drive: 64th Street to Pleasant Pond Drive
  • Ranchland Dr. (East): Byron Center Ave. to Pleasant Hill Dr.
  • Ranchland Drive (West): Byron Center Avenue to End
  • Sunflower Drive: 64th Street Southerly to End
  • VanSingel Drive: Pleasant Hill Drive to Pleasant Pond Drive

    Letter to Residents

    How to prepare for Neighborhood Repaving Project

Wolverine Boulevard 10 Mile Road to 11 Mile Road Mill & Fill TBD TBD Two-way traffic maintained

This project includes the cold mill of existing HMA over existing rubberized concrete pavement and placement of two (2) courses of new Hot Mix Asphalt (HMA) in 4-lane boulevard section. Two-way traffic will be maintained.

Northland Drive 11 Mile Road to 12 Mile Road Mill & Fill TBD TBD KCRC Two-way traffic maintained

This project includes a full depth cold mill of the existing 5-lane asphalt surface and placement of two (2) courses of HMA.  Milling and paving work will be phased to maintain 2-way traffic at all times.  Bid with Wolverine Boulevard segment.

Northland Drive Lake Street to N. Co. Line Mill & Fill TBD TBD

This project includes the cold mill of existing asphalt surface and placement of new Hot Mix Asphalt (HMA) – Include with Montcalm CRC Project

Northland Drive 18 Mile Road to Ritchie Avenue Pavement Replacement TBD TBD KCRC Detour for Through Traffic

This project includes installation of underdrains, placement of 4-inch layer of aggregate over existing asphalt pavement (over concrete pavement), the pulverizing of  aggregate and asphalt, grading and placement of two (2) courses of HMA.  Through traffic will be detoured.

Division Avenue West River Drive to 6 Mile Road Mill & Fill TBD TBD KCRC Detour for Through Traffic

This project includes a full depth cold mill of existing two (2) lane and four (4)-lane asphalt surface and the placement of two (2) courses of HMA.  Through traffic will be detoured.

68th Street Eastern Avenue to Kalamazoo Avenue Mill & Fill TBD TBD KCRC Two-way traffic maintained

This project includes the cold milling of the existing 4-lane asphalt surface and placement of two (2) courses of HMA. Upgrade sidewalk ramps to meet current ADA requirements. Two-way traffic will be maintained.

6 Mile Road Alpine Avenue to Pine Island Drive Crush & Shape TBD TBD KCRC Detour for Through Traffic

This project includes a crush and shape of the existing asphalt surface and placement of two (2) courses of hot mix asphalt (HMA).  Through traffic will be detoured.

4 Mile Road Coit Avenue to Plainfield Avenue Mill & Fill TBD TBD KCRC Two-way traffic maintained

This project includes full-depth cold milling of existing 3-lane asphalt surface and placement of 2 courses of new HMA. Two-way traffic will be maintained.

18 Mile Road (Tyrone Bridge #21) over Rogue River Bridge Improvement TBD TBD KCRC Detour

Bridge superstructure replacement project to remove the existing concrete deck and steel beams and replace with galvanized steel beams and reinforced concrete deck and railing. Traffic will be detoured.

Lincoln Lake Avenue (Spencer Bridge #22) over Clear Creek Bridge Rehabilitation TBD TBD KCRC

Culvert rehabilitation project to repair deteriorated portion of the existing triple corrugated metal pipe arches with reinforced concrete placed on the bottom internal portion of the galvanized metal culverts.

Knapp Street (Ada Bridge #5) over the Grand River Bridge Improvement TBD TBD Two-way traffic maintained

This bridge preservation project includes reinforced concrete deck patching and epoxy sealing. Partial clean and paint Steel Girders. Two-way traffic to be maintained using portable traffic signals.

Burton Street at Patterson Avenue Intersection Work TBD TBD KCRC

Modify and upgrade existing traffic signal, with box span configuration, LED signal heads, backplates and updated detection.

Cascade Road 36th Street to Whitneyville Avenue Reconstruction TBD TBD KCRC Detour for Through Traffic

Widen existing 2-lane portion to 3 lanes.  Work includes earthwork, concrete curb and gutter, storm sewer, drainage, HMA pavement, pavement markings and restoration. Through traffic will be detoured.

100th Street Hanna Lake Avenue to East Paris Avenue Reconstruction TBD TBD KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, HMA pavement, pavement markings and restoration. Through traffic will be detoured

68th Street Glen Hollow Drive to Hanna Lake Avenue Reconstruction TBD TBD KCRC Two-way traffic maintained

Widen existing 4-lane portion of 68th Street to 5 lanes.  Work includes earthwork, concrete curb and gutter, storm sewer, drainage, concrete sidewalk (funded by Gaines Township), HMA pavement, pavement markings and restoration. Two-way traffic will be maintained. 

KCRC's Five-year Improvement Plan TBD TBD

DOWNLOAD: KCRC's Five-year Improvement Plan