Road Limits Work Start Completion Authority Traffic
KCRC's Five-year Improvement Plan TBD TBD

DOWNLOAD: KCRC's 2023 Budget and Five-year Improvement Plan

Road Limits Work Start Completion Authority Traffic
Cascade Road 36th Street to Whitneyville Avenue Reconstruction 04/03/23 06/30/23 KCRC Detour for Through Traffic

Road reconstruction and widening to add dedicated left-turn lane. Cascade Road will be CLOSED to through traffic with a posted detour using 36th Street to Buttrick Avenue. Work includes earthwork, concrete curb and gutter, storm sewer, drainage, HMA pavement, pavement markings and restoration.

This project will also include construction of a township-funded, non-motorized path on the easterly side of Cascade Road between 36th Street and Kenrob Drive.

10 Mile Road Pine Island Drive to Algoma Avenue Reconstruction 04/03/23 08/07/23 KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, water main (Plainfield Twp), HMA (hot mix asphalt) pavement, pavement markings and restoration. (Tree removal began March 27).10 Mile Road is scheduled to be open to traffic by August 7 with final restoration completed by October 28, 2023.

Reeds Lake Boulevard (EGR) Hall Street to Manhattan Mill & Fill TBD TBD KCRC Detour for Through Traffic

This project is being completed in partnership with the City of East Grand Rapids.

  • Cold mill existing two-lane asphalt surface and place 1-2 courses of HMA pavement.
Parnell Avenue/Settlewood Drive M-21 (Fulton Street) to Foreman Street Crush & Shape TBD TBD KCRC Detour for Through Traffic

Crush and shape the existing asphalt surface and place two courses of HMA pavement. 

Honey Creek Avenue 2 Mile Road to 4 Mile Road Crush & Shape TBD TBD KCRC Detour for Through Traffic

Crush and shape the existing asphalt surface and place two courses of HMA pavement. Project will be scheduled spring/summer 2023. 

  • Honey Creek Avenue from 4 Mile Road to 5 Mile Road will receive chip seal and fog seal preventive maintenance surface treatments during the 2023 construction season
Eastern Avenue 68th Street to 76th Street Mill & Fill TBD TBD KCRC Two-way traffic maintained

Cold mill existing three-lane asphalt surface and place two courses of HMA pavement. Two-way traffic be maintained.  Project start in spring to be completed by June 2, 2023.  

Division Avenue 6 Mile Road to 7 Mile Road Mill & Fill TBD TBD Detour for Through Traffic

Cold mill existing two-lane asphalt surface and place two courses of HMA pavement. Targeted for Spring/summer 2023 start.

Buttrick Avenue Grand River Drive to Thornapple River Drive Mill & Fill TBD TBD KCRC Detour for Through Traffic

Full Depth Cold mill existing 2-lane asphalt surface and place 2 courses of HMA pavement. Project to be scheduled after July 9, 2023.

84th Street Wingier Avenue to Freeport Avenue Resurfacing TBD TBD KCRC Detour for Through Traffic

Crush and shape the existing asphalt surface and place 2 courses of HMA pavement. 

100th Street East Paris Avenue to Patterson Avenue Reconstruction TBD TBD KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, HMA pavement, pavement markings and restoration. Tree removal has been completed. 

84th Street Hanna Lake Avenue to East Paris Avenue Reconstruction TBD TBD KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, HMA pavement, pavement markings and restoration.

18 Mile Road (Tyrone Bridge #21) over Rogue River Bridge Improvement TBD TBD KCRC Detour

Bridge superstructure replacement project to remove the existing concrete deck and steel beams and replace with galvanized steel beams and reinforced concrete deck and railing. Traffic will be detoured. Project is anticipated for late summer/fall 2023.

KCRC's Five-year Improvement Plan TBD TBD

DOWNLOAD: KCRC's 2023 Budget and Five-year Improvement Plan