Road: Herrington Avenue
Limits: 3,000 feet south of 10 Mile Rd to 10 Mile Rd
Work: Utility Work
Start: 05/17/22
Completion: 07/01/22
Traffic: Detour
Authority: Utility
The project includes approximately 3,000 ft. of 16” water main installation along the west side of Herrington Avenue. Work also includes a 30” steel casing under 10 Mile Road installed by bore and jack methods.