Road: Northland Drive
Limits: 12 Mile Road to 14 Mile Road
Work: Mill and Fill
Start: 07/10/23
Completion: 08/07/23
Traffic: Lane Closures
Authority: KCRC
Full Depth Cold mill existing 5-lane asphalt surface and three courses of HMA pavement. Milling and paving work will be phased to maintain two-way traffic at all times.