Road: Morgan Mills (Oakfield Bridge 9)

Limits: Over Wabasis Creek

Work: Bridge Improvement


Start: 10/02/23

Completion: 11/18/23


Traffic: Closed to All Traffic

Authority: KCRC

Contractor: Davis Construction Company

Removal of twin corrugated metal pipe arches (CMPAs) and replacement with twin 148" span x 93" rise twin CMPAs. Project will require an extensive cofferdam. Permanent sheet piling will be installed along west side of roadway, near adjacent boat ramp. Project includes new guardrail, and roadway reconstruction at the immediate installation. River flow will be maintained for small boat traffic. 


Roadway traffic will be detoured via 12 Mile Road, Lincoln Lake Avenue and 14 Mile Road.