Project Details

< Back

Information

Road: Pine Island Drive

Limits: 6 Mile Road to Buth Drive

Work: Utility Work


Start: 09/19/22

Completion: 10/14/22


Traffic: Detour

Authority: Utility

Contractor: Dean's Excavating

16-inch water main installation crossing Pine Island Drive at 6 Mile Road intersection and continuing north along the east side of Pine Island Drive to Buth Drive