Road: Sparta Bridge 28
Limits: 13 Mile Road .3 miles west of Alpine Avenue
Work: Bridge Improvement
Start: 04/05/21
Completion: 05/05/21
Traffic: Closed to All Traffic
Authority: KCRC
Contractor: J. E. Kloote Contracting
Funding: $230,000 - KCRC
This bridge rehabilitation project includes spot concrete box beam replacement, deck waterproofing, concrete abutment repair and new HMA surface. This project will be done in conjunction with the 13 Mile paving project slated to begin in early May. After bridge work is completed, and the paving contractor (Michigan Paving & Materials) for the 13 Mile project has mobilized, base paving operations will take place at the bridge and adjacent areas.