Project Details

< Back

Information

Road: Wolverine Boulevard

Limits: 10 Mile Road to 12 Mile Road

Work: Mill and Fill


Start: 07/27/22

Completion: 09/13/22


Traffic: Lane Closures

Authority: KCRC

Contractor: Michigan Paving and Materials

The project will consist of hot mix asphalt cold milling and resurfacing, aggregate shoulders, restoration, and pavement markings. 

The project will be done in phases while maintaining 2-way traffic:

  • Phase I - The outside lanes will be milled and paved through HMA base course. 
    • During Phase I, 11 Mile Road will be closed. 
  • Phase II - The inside lanes and crossovers will be milled and paved through HMA base course. 
  • Phase III - The intersection of 12 Mile Road will be milled, and the entire project will be paved with HMA top course